Contracts & Estimates
Garage door contracts in Ontario: direct agreements, the 10-day cancellation right and the 10 per cent estimate rule
What should the contract say about a deposit for a new garage door in Ottawa?
A contract for a new garage door in Ottawa should spell out the deposit amount in writing before any money changes hands, and Ontario's Consumer...
My final bill is higher than the garage door estimate: what does Ontario law say?
When a consumer agreement includes an estimate, the Ontario Consumer Protection Act, 2002 says the supplier "shall not charge the consumer an amount...
Changes to a garage door job in Kanata after signing: how should they be recorded?
Record every change in writing before the work it covers is done. Under the Consumer Protection Act, 2002, s.10(1), if a consumer agreement includes...
When does the 10-day cancellation on an Ontario garage door contract start?
The 10-day window is set by the Consumer Protection Act, 2002. Under s.43(1) of the Act, a consumer may cancel a direct agreement "at any time from...